ENCLAVE ONE

Enclave One is coming to life quickly. Privacy walls with stone masonry accents are going up, stairs are getting poured, garages have been sided, and the pool area continues to progress. Building 1’s interior finishes are nearing completion (see photo above). In Buildings 2 and 3, tiling is complete, trim and door installation is nearing completion, and appliances will be installed later this month. Building 4’s tiling is also complete, and interior finishing work is ongoing. Buildings 5 and 6 are getting drywall installed.

 

ENCLAVE TWO

All foundations have been poured in Enclave Two, and a majority of the Villas have gone vertical as framing continues through to Building 12. Plumbing, mechanical, and electrical work is ongoing in Buildings 7 to 10. Over half of the roofs are completed.

 

ENCLAVE THREE

Construction in Enclave Three continues to push ahead. Trenching has begun for Building 14, and underground utilities will be installed later this month.