All exterior doors and windows have been installed in Buildings 1 and 2 of Enclave One, and interior finishing work has begun, including tiles, doors, trim, and cabinets. In Buildings 3 and 4, drywall installation is nearing completion and in Buildings 5 and 6, mechanical and electrical work is underway. We are excited to see that the pool, hot tub, and water features of Enclave One are taking shape as well. Enclave Two continues to go vertical as framing has been completed on Buildings 7, 8, and 9 and continues on Buildings 10 and 11. Slabs will be poured for Buildings 12 and 13 in the coming days. In Enclave Three, utility installation is nearing completion and Building 14 layout will begin soon thereafter.