ENCLAVE ONE

Enclave One exteriors are coming to life. Painting and siding is underway, mature palm trees have been planted throughout the Enclave, and the rock formations in the pool area are completed. Buildings 2 and 3 are seeing cabinet installation and continued work on interiors. Interior finishing work continues on Buildings 4, 5, and 6.

 

ENCLAVE TWO

Framing is underway in all Buildings. Buildings 7 and 8 have mechanical and electrical rough-in work almost complete, and dry wall hanging has commenced. In Buildings 9 and 10, electrical installation has begun, and windows and exterior doors are being placed and installed. Buildings 11 and 12 have ongoing plumbing activities and roof tile installation happening.

 

ENCLAVE THREE

Construction in Enclave Three continues to push ahead. Trenching has begun for Building 14, and underground utilities will be installed later this month.