Enclave One

Daily progress is visible as walking paths, landscaping, and exterior finishes come together to define the first Garden Enclave. Auto courts are being poured, showcasing Luana Garden Villa’s designated parking areas and private garages. The pool amenity deck is being prepped to be poured with concrete in the coming weeks. The interior finishes in Buildings 1 – 4 are nearly complete as fixtures and accessories are being installed. In Buildings 5 and 6, installation of cabinets, countertops and appliances is underway.

 

Enclave Two

Excavation of the pool area in Enclave Two has begun. Interior finishes are ongoing in Buildings 7 and 8, including tiling, interior painting, and cabinet installation. In Buildings 9 to 11, mechanical, electrical, and plumbing installation continues and drywall installation has begun. Roof installation and finish framing is ongoing in Building 12. Building 13 is now vertical, with second floor framing complete and contractors preparing to install the trusses.

 

Enclave Three

Framing activities have begun in Enclave Three as Building 14 has gone vertical, with the first floor already complete. Across the rest of the Enclave, electrical and underground plumbing installation is underway and foundations are being prepped for excavation. Concrete pouring for foundations in Buildings 16 through 18 will begin shortly.