Enclave One is now complete and happy homeowners are enjoying their new resort homes!

Enclave Two is progressing well, with completion estimated to be within the first quarter of 2020. The pool deck is now poured and mature palm trees are planted in the common landscape areas.

Buildings 7 and 8 are nearing completion and furnishings will be installed in these residences in January. Interior finishing work continues in Building 9 and in Building 10, interior painting is underway. Cabinets are being installed in Building 11 and inside Building 12, tile work and door installation is underway. Contractors are now taping the drywall inside Building 13.

Enclave Three construction moves ahead with estimated completion to be summer of 2020. The roof installation is complete for Buildings 14, 17 and 18. Framing is complete for Building 16 and the framing crew is now moving to the second story of Building 15, the last building to be framed on the project!